What’s the plan for Las Olas Boulevard west of SE 17th Avenue? The corridor redesign, explained

The City Commission has approved a conceptual redesign of Las Olas Boulevard from Andrews Avenue to SE 17th Avenue — the Downtown, Retail Shops, and Colee Hammock segments — with the Retail Shops median removed, and directed the design team to advance the corridor to 60% design plans. A $1 million state grant for safety and ADA upgrades followed in May 2026.

Intelligent real estate, personally delivered.

Photo: Infrogmation, CC BY-SA 4.0, via Wikimedia Commons.

From vision plan to an approved concept

The redesign grows out of the 2021 Las Olas Boulevard Vision Plan, and WSP USA has been designing the western corridor since May 2024. In December 2025 the Commission supported the preferred concepts for all three segments, leaving one question open: whether the Retail Shops segment would keep its median. On February 3, 2026, the Commission settled it — approving the concept with the Retail Shops segment designed without the median (Resolution 26-27) and directing staff to advance the whole corridor to 60% design plans.

The design work in the record is specific: the traffic analysis found minimal impact on intersection levels of service, recommended removing the traffic signal at SE 9th Avenue (a warrant analysis found it no longer needed), and accepted removing the center turn lane there. The city also modeled the corridor against its updated stormwater system and found each segment meets the citywide level-of-service standard for a 10-year storm in 2025, 2040, and 2070 conditions — so no additional stormwater capacity is proposed as part of the project.

On May 5, 2026, the Commission approved a $1,000,000 FDOT state appropriation grant for Las Olas safety improvements and ADA upgrades along the western corridor. And on October 6, 2026, a Las Olas homeowner brought the other side of the drainage question to the Commission — a resident presentation on the project’s drainage impacts on private properties. I'm Sean Strahler — Sailboat Bend and Fort Lauderdale specialist — a Real-ativity agent who lives there. Design is not construction: the 60% plans come first, and I date each milestone on the Downtown page as it is scheduled.

Quick facts

  • The corridor: Las Olas Blvd, Andrews Avenue to SE 17th Avenue — Downtown, Retail Shops, and Colee Hammock segments
  • Roots: 2021 Las Olas Boulevard Vision Plan; WSP USA designing since May 2024
  • Concept approved: February 3, 2026 (Resolution 26-27) — Retail Shops segment without the median
  • Next step ordered: Advance the corridor to 60% design plans
  • State money: $1,000,000 FDOT appropriation grant for safety and ADA upgrades, approved May 5, 2026
  • Drainage: City modeling: corridor meets the 10-year storm standard; resident drainage concerns presented October 6, 2026

Common questions

Was the Las Olas median kept?

No. The December 2025 concepts left the Retail Shops median as the open question; the February 3, 2026 approval chose the design without the median.

When does construction start?

There is no construction schedule yet. The Commission directed the design to advance to 60% plans — construction decisions come after design, funding, and phasing are set.

Will the redesign handle flooding?

The city’s updated stormwater model shows all three segments meeting the citywide standard for a 10-year storm through 2070 conditions, and no extra stormwater capacity is proposed. Residents raised drainage impacts on private properties at the October 6, 2026 meeting, and that concern is on the public record.

What does the $1 million grant pay for?

Safety improvements and ADA upgrades along the Las Olas western corridor, under a Florida Department of Transportation state appropriation grant agreement approved May 5, 2026.

More updates like this

This post is the longer read. The running, dated log for this neighborhood — every city item as it happens — lives on the Downtown neighborhood page.

Questions about Downtown — or what any of this could mean for your home? I'm happy to talk it through.

Sean Strahler, Real-ativity
Phone: (412) 897-0023
Email: SeanStrahler@Real-ativity.com
Florida Sales Associate · License SL3647352

Find me: Facebook  |  YouTube  |  Real-ativity  |  Leave a Google review
Agent profiles: Zillow  |  Realtor.com  |  Homes.com

Intelligent real estate, personally delivered.